Infrastructure works at water treatment site
← All Projects

Water & Utilities

Hunter Valley Water Treatment Plant Upgrade

Client

Hunter Water Corporation

Location

Singleton, NSW

Value

$31M

completed

Client

Hunter Water Corporation

Location

Singleton, NSW

Contract Value

$31M

Duration

18 months

Completed

August 2023

Team Size

55 peak

Staged upgrade of an operating water treatment plant serving 85,000 customers, requiring construction to proceed while maintaining continuous treatment capacity.

Certifications

ISO 9001ISO 14001ISO 45001

The Challenge

Upgrading a treatment plant that cannot be taken offline - 85,000 people depend on it for potable water supply. All construction had to be staged around operational requirements, with tie-ins requiring precise shutdown windows of less than 6 hours.

Our Solution

Le Gardenz engaged under an Early Contractor Involvement (ECI) arrangement, working with the design team 4 months before contract award to optimise staging. Tie-in windows were pre-planned with the operator, and Le Gardenz pre-fabricated all pipework and components off-site to minimise in-plant construction time.

Scope of Works

01

New sedimentation basin - 4 ML capacity

02

Filtration system upgrade - 12 filter cells

03

Chemical dosing system replacement

04

SCADA and instrumentation upgrade

05

Civil, structural, and architectural works

06

Commissioning and operator training

Outcomes

  • -

    Continuous water supply maintained throughout all 14 construction stages

  • -

    Project completed 4 weeks ahead of programme

  • -

    Final cost 1.2% under contract sum

  • -

    Zero notifiable incidents across 180,000 worked hours

  • -

    Achieved all 47 operational milestones without service interruption

Site construction progress
Water infrastructure construction